July 2012
Wellness Center Update

The Mercy Wellness Center remains closed as renovations begin to repair significant damage caused by the flood.

 

The anticipated completion and reopening date for the Center will be announced once contractor and material availability is determined.

 

Needed renovation work includes new insulation and drywall for the bottom two feet of the walls, along with new carpeting and gym floor. Doors, casework and lockers also need to be replaced. Lead time on re-ordering these items can be 4-6 weeks. In addition, much work is required to repair the tile showers.

 

We are also working on a way to address the time missed in June by those with paid memberships.  More information about this issue will be available once details are finalized.  

 

We thank you for your patience as we work to restore services.

 